Instrument Commissioning
------------------------

+ NAOS/CONICA: PAE (Preliminary Acceptance Europe) and dry-runs took
place in Paris in July. Nicolas, Yves and myself participated in the dry-runs.
As a result, we came back home with new requirements for P2PP and change
requests for ETC. Work on the pipeline has progressed.
After PAE, the decision was made to wait two more months before shipping
the instrument to Chile. This means that in the best case, we will have a first
commissioning at the end of the year.

+ VIMOS: PAE did not take place in July. The next possible time slot will be
September.

+ FLAMES: The installation of OzPoz is planned for december and its commissioning
for January.

+ FORS1 was moved to UT3 end of July.

+ FORS2: The upgrade to the new CCDs will take place in November. It will
require upgrades to the DO and pipeline. FTU will be used, as for VIMOS, to
split files on the Instrument Workstation.



DFS Commissioning
-----------------

A DFS commissioning will have to take place before the end of the year. We have
this time more flexibility to choose the dates as there will not be any VLTSW
installation (OCT2001 does not go to Paranal).
The installation/integration dates will be derived from the availability of
the components we deliver:

- Java OT
- OLAS: support for HP file system size limitation
- ASTO and new robot
- P2PP with EVM; TBC


General
-------

+ A version of 2002 budget must be ready for internal DMD discussion at the
end of the month

+ A DMD management retreat will take place on August 27th. Development priorities
for the next six months will be discussed

+ The OmegaCam FDR will take place on September 21th.