* LIST OF OPEN ACTION ITEMS *
================================

Last update: Tue Jul 24 09:36:10 MET DST 2001

----------------------------------------------------------------------------------------------
ID Chronological number (to be updated manually).
Comp Name of the DFS project or component (SAF, VCSOlac, FrameIngest, DO, RBS,
-pipe, ...). In most of the cases, it's enough to have a To-Do list
per DFS project (e.g. SAF). However, project managers may decide to have a
To-Do list per component, if appropriate.
Origin Meeting name/review/date during which the action item was originated.
Type ACTION= for a normal action item;
BUG= for an item related to a bug report;
CHANGE= for an item related to a change request.
Prior Priority= LOW, HIGH, CRITIC
DueDate Either a specific date (YYYY-MM-DD) or a specific new release (in that case,
corresponding date has to be specified in associated DFS component schedule).
Resp Responsible name; even if several persons can be involved in the action item, one
should be responsible for follow-up.
Status INIT= to be started; SUSPEND= suspended, waiting for external inputs;
PROGRESS= action in progress.
Description
Detailed description. For BUG and CHANGE, specify the SPR number and a short
description: the complete description of the SPR must be found in Action Remedy.

----------------------------------------------------------------------------------------------
ID Comp Origin Type Prior DueDate Resp Status
Description
----------------------------------------------------------------------------------------------

0005 ETC ParisMeeting/21-12-2000 ACTION HIGH 2001-03-25 LR PROGRESS
GIRAFFE ETC prototype implementation on dev. machine

0006 ETC ParisMeeting/21-12-2000 ACTION HIGH 2001-04-23 LR INIT
GIRAFFE ETC installation at Meudon Observatory

0007 ETC ParisMeeting/21-12-2000 ACTION HIGH 2001-05-18 LR INIT
GIRAFFE ETC sky spectrum module

0008 ETC ParisMeeting/21-12-2000 ACTION HIGH 2001-05-29 LR INIT
VISIR ETC database integration

0009 ETC P69 Release Prep. ACTION HIGH 2001-06-17 LR INIT
ISAAC, FORS ETCs correction

0010 ETC P69 Release Prep. ACTION HIGH 2001-07-16 LR INIT
CONICA Spectroscopy ETC prototype

0011 ETC P69 Release Prep. ACTION HIGH 2001-08-01 PB INIT
P68 Phase 2 release of ETCs including update of FORS, ISAAC, VIMOS, UVES, CONICA Ima ETCs

0012 ETC P69 Release Prep. ACTION HIGH 2001-08-13 LR INIT
CONICA Spectroscopy ETC Internal Release

0014 ETC P69 Release Prep. ACTION HIGH 2001-08-31 PB INIT
P69 Phase 1 release of ETCs including GIRAFFE, VISIR, CONICA Spectroscopy