Status Highlights
- The MIRI team has now completed two cryo-test campaigns with the MIRI VM
- These give great confidence in expected MIRI performance and our ability to calibrate it
- Lessons learned have been applied to the flight design of the ICE and FPE
- Completed environmental qualification testing for most of the hardware
- Wheel mechanism assemblies qualification tests complete next year
- Completed manufacture and assembly of the three flight focal plane modules
- One is already ready for delivery, the other two in final stages of acceptance testing
- Started assembly of all the FM optical sub-assemblies
- Some FM Units are delivered and now being stored
- Science Team and STScI have made great progress in defining key aspects of MIRI operations
MIRI Test and Calibration Team
- MIRI Cryo-testing is carried out by an integrated international team supported by ALL the MIRI partners (i.e. all the EC countries, STScI JPL, GSFC, Arizona, Ames, ESA)
- Team organization and participation has been a great success of the test campaign
- Some 40 people in total contributed
- Mixture of experiences instrument scientists and people testing an infrared instrument for the first time
- This is a team that will carry out the flight performance verification tests, ground calibration of the flight instrument, flight calibration, in orbit checkout etc.