SMOV Status & Planning Meeting Minutes 02/21/97

SMOV Status & Planning Meeting Minutes

Meeting Date: 02/21/97


STATUS REPORTS

1.  SM & Observatory Status

	MOSES status reports:
	-PCS - all nominal - FHST/FHST alignment are good.  FGS1R
		table parameters to be uplinked after inital guide
		star acquisition tomorrow.
	-EPS - No SA transients or drive torques are now
	      	observed.
	     - ESTR2 has been powered off because of increasing 
		temperature/pressure correlation.  Meeting to follow
		this one to determine how to proceed with SMS053 and
		until the behavior can be observed at a new sun angle.
	-DMS - nominal.  SSR has been excersized several times for
		playback of Functional Test data, but not yet through 
		the SAA.  Deploy data playback later today will be
		through the SAA.  No major concerns at this point.
		The NSSC1 load has been started.

2.  WFPC2 Status - nominal - no change from last report
				
3.  NICMOS Status - nominal - VCS and forward optics temperatures behaving
		as expected.

4.  STIS Status - Low-level bus noise still persists.  NSSC1 rotation matrices
		need to be uplinked.

5.  FGS status - nominal - no change from last report

6.  FOC/COSTAR status - Sink temperature is
	about 3 deg warmer compared to pre-SM2 measurements.
	Otherwise, nominal.

PLANNING REPORTS

1.  Status of Upcoming SMSs

	- HS051 (H&S SMS) - currently executing.

                The goal is to run all of the SMSs through SMS069 by
		Sunday for input to commanding review in order to 
		get a jump on TDRS requests in forecast period.

 	- SMS053 (1st SMOV Science SMS) - Finals have been delivered.
			and SMS has been signed off.  Ready for uplink.
				
	- SMS055 - finals are being prepared for review.
 
   	- SMS058 - currently being built

	- SMS058H - contingency SMS058 in case WFPC2
 			contamination is seen in SMS055.

  	- SMS062 - replanned test calendar complete 

   	- SMS065 - replanned test calendar complete

   	- SMS069 - replanned test calendar complete

  	- SMS072 - replanned test calendar complete

2.  Replans - none

OPERATIONAL ISSUES - None